X

Enquire Now

JOINT PRESS STATEMENT BY UPL AND THE UPL MULTI-STAKEHOLDER FORUM (MSF)

Date: 01 Jul 2022 | Author: CORPORATE COMMUNICATIONS

Tags: CORNUBIA

JOINT PRESS STATEMENT BY UPL AND THE UPL MULTI-STAKEHOLDER FORUM (MSF)

01 July 2022

UPL South Africa and Interim Multi-Stakeholder commit to working together

For the first time since the devastating fire at UPL’s Cornubia Warehouse that was started during the July 2021 civil unrest, the UPL management team and members of the interim multi-stakeholder forum (MSF) that was established by MEC Ravi Pillay met yesterday (30 June 2022) to explore how both parties can work together moving forward. 

JOINT PRESS STATEMENT BY UPL AND THE UPL MULTI-STAKEHOLDER FORUM (MSF)

01 July 2022

UPL South Africa and Interim Multi-Stakeholder commit to working together

For the first time since the devastating fire at UPL’s Cornubia Warehouse that was started during the July 2021 civil unrest, the UPL management team and members of the interim multi-stakeholder forum (MSF) that was established by MEC Ravi Pillay met yesterday (30 June 2022) to explore how both parties can work together moving forward.

UPL explained that communication between it and the MSF to date had not been helped by the fact that the MSF and its terms of reference had not been finalised by the MEC, and that it was reluctant to formally engage until that had been done. It expressed its frustration that the enormous sums of money invested in clean-up and the progress that had been made by its team of experts had not been adequately acknowledged. It expressed its concerns at biased reporting that did not reflect the substantial reduction of contaminants in the affected environments and the return of life throughout the impact zone. It recognised in principle the role of a stakeholder forum, but queried how the MSF would function within in the statutory compliance processes, and what its powers and representivity would be.

For its part the MSF expressed its concern that UPL’s refusal to engage with it gave the impression that information relevant to the affected communities was being withheld, was thus counter- productive to everyone’s interests, and contrary to industry practice for chemical incidents such as this. It stressed the right of communities to know the risks to which they are exposed, and what steps are being taken in response - which is only achieved by inclusion in relevant decision-making. It queried why UPL and the authorities have been reluctant to involve the MSF in the incident responses to date to the extent that they should have.

There was a frank and cordial exchange of views. It was agreed at the culmination of the meeting that great progress had been made in understanding each side’s perspectives, and that a path to formal engagement and collaboration should be pursued to tackle the remaining challenges arising from the incident.

The group agreed on the following as the way forward:

  • The terms of reference of the MSF would be revised to clarify the role of the MSF and to reflect the consensus reached at the meeting;
  • The stakeholder base would be reviewed to ensure that all stakeholders are represented, and would include the landowners whose properties were contaminated in the incident;
  • A presentation would be made to the MSF within the next month by UPL’s specialists, at which the MSF would be appraised of current progress in the incident response and be able to raise questions and obtain clarity.
  • Further engagements will be discussed thereafter, including the manner in which the authorities, UPL and the stakeholders would interact to further progress toward a formal and acceptable strategy, which can be implemented as a matter of extreme urgency in the best interests of all affected parties.

The parties have committed themselves to working together as the processes unfold, and expressed the view that this was a very significant step forward.

 

ENDS///

Media Enquires

Thabi Ndhlovu - +27 61 993 6672

Share this article